The construction of six laning of Gurgaon-Jaipur National Highway project was started w.e.f 03.04.2009 with construction period of 2.5 year. The project could not be completed on schedule completion date 02.10.2011 and construction is going on. As on date, the physical progress is about 91%.
The main reasons for delay in completion of above project is as under:
(i) Delay in land Acquisition due to delay in disbursement of compensation by competent authority of land acquisition
(ii) Delay in removal/relocation of government structures and religious structures
(iii) Delay in shifting of High Tension lines, Electrical utilities and water supply utilities
(iv) Delay in handing over of forest & irrigation land by Haryana Government
(v) Slow progress of work by the Concessionaire due to financial crunch
The project is being monitored at the highest level. A series of High Level Meetings were held wherein all the stake holders i.e. the Concessionaire, Independent Engineer, Lenders, Chief Secretary of Rajasthan and Chief Secretary of Haryana were present to sort out bottlenecks to complete the project at the earliest.
The construction was already started w.e.f 03.04.2009 and is likely to be completed by 30.06.2016 as per supplementary agreement.
This information was given by Minister of State for Road Transport & Highways, Shri Pon. Radhakrishnan in a written reply to a question in the Rajya Sabha today.
The main reasons for delay in completion of above project is as under:
(i) Delay in land Acquisition due to delay in disbursement of compensation by competent authority of land acquisition
(ii) Delay in removal/relocation of government structures and religious structures
(iii) Delay in shifting of High Tension lines, Electrical utilities and water supply utilities
(iv) Delay in handing over of forest & irrigation land by Haryana Government
(v) Slow progress of work by the Concessionaire due to financial crunch
The project is being monitored at the highest level. A series of High Level Meetings were held wherein all the stake holders i.e. the Concessionaire, Independent Engineer, Lenders, Chief Secretary of Rajasthan and Chief Secretary of Haryana were present to sort out bottlenecks to complete the project at the earliest.
The construction was already started w.e.f 03.04.2009 and is likely to be completed by 30.06.2016 as per supplementary agreement.
This information was given by Minister of State for Road Transport & Highways, Shri Pon. Radhakrishnan in a written reply to a question in the Rajya Sabha today.
Courtesy: pib.nic.in