Deadlines set for key infrastructure project investments

A meeting of the Steering Group appointed by the Prime Minister to accelerate Infrastructure Investment in its first meeting has finalized deadlines with time lines for the intermediate steps for key infrastructure projects. The progress on the intermediate steps will be monitored on a regular basis.  The deadlines will ensure that  Ministries / Departments are clear about not just the overall deadline but also all the intermediate steps that need to be completed so that there are no slippages.
            The Principal Secretary to PM has directed all Ministries/ Departments to nominate a Nodal Officer each, of the rank of a Joint Secretary or above, who will report on a weekly basis on the progress of their department's project(s). The names would be intimated to the PMO by 26.7.2013.
The meeting decided on the following deadlines


2. In addition, the following were also agreed to:
i)   Mumbai Elevated Rail Corridor Project: The issue of whether the RFQ will be reissued will be resolved by M/o Railways within a week.
ii)   Eastern DFC: M/o Railways will provide exact timelines on completion of the Khurja-Kanpur, Kanpur-Mughalsarai and Mughalsarai-Sonnagar stretches. On the Ludhiana-Dadristretch for which funding has yet to be fully tied up, the Steering Group will review the matter in 4 weeks, after the committee on financing projects in Railways completes its work.
iii)   Expressways: While pursuing the three Expressways mentioned by MoRTH (Eastern Peripheral, Delhi-Meerut, Mumbai-Vadodara), MoRTH will also work on the financial model for the Delhi - Jaipur Expressway. The pre-
feasibility will be completed by 15.8.2013 and the progress on this will also be  monitored for early award.
iv)  UMPPs: RFQs, which were invited as per old documents, will be now based on new documents.
 v)  Transmission  projects:  M/o Power will try to  award the 13  identified transmission projects as per the agreed timelines.
 vi)  New Airports: In addition to Navi Mumbai, MoCA will make efforts to move ahead on Goa (Mopa) airport as well.
vii) OMT of Airports: MoCA will work towards awarding OMT contracts for 4-5 airports by 31.3.14
Coutesy: (pib.nic.in) Press Information Bureau.

1 comment:

Unknown said...


I m very glad to know that Wegmans Group up Office Space in as well as Lockable Space in Greater Noida. Find the details of new project Trustone City Noida this is the name of this new commercial project.

Extension of Emergency Credit Line Guarantee Scheme through ECLGS 2.0 for the 26 sectors identified by the Kamath Committee and the healthcare sector

Extension of the duration of Emergency Credit Line Guarantee Scheme (ECLGS) 1.0 The Government has extended Emergency Credit Line Guarantee ...