Tuesday, 18 July 2017

Status of Construction of Bridges in GOA on NH-17

In a written reply to a question in the Rajya Sabha today, the Minster of State for Road Transport & Highways and Shipping, Shri Mansukh L. Mandaviya gave the status of  construction of the bridges proposed on National Highway-17 in Goa sector as follows:-

S.No
Name of the bridge
Status of construction
Target of completion
Cost of construction (in Rs. Crores)
Mode of financing
Parties involved
1.
Zuari river bridge
In Progress
(1%)
23/11/2019
936.40
Financed by Ministry under budgetary resources
Government of India
2.
Mandovi river bridge
In Progress
(60%)
31/05/2018
517.00
Financed by the State Government and National Bank of Agriculture and Rural Development (NABARD)
Government of Goa through Goa State Infrastructure Development Corporation (GSIDC)
3
Talpona, Galjibag, Maxem bridges as part of Canacona bypass from km 68/00 to km 85/740 of NH-17 in the state of Goa on EPC mode
In Progress
(36%)
06/12/2017
280.16
Financed by Ministry under budgetary resources
Government of India


Courtesy: pib.nic.in

No comments:

NHAI launches mobile App MyFASTag and FASTag Partner

Apps will facilitate the availability of FASTags for Electronic Toll Collection National Highways Authority of India launched two mobi...