In Namami Gange project total number of 155 projects for various activities such as sewage infrastructure, river front development, ghat and crematoria, ghat cleaning, rural sanitation etc. has been sanctioned.  Out of 155 projects 39 numbers of projects have been completed so far.

Cleaning of river Ganga is being carried out through various activities including treatment of municipal sewage, treatment of industrial effluent, river surface cleaning, rural sanitation, afforestation and biodiversity etc. The municipal sewage being generated in cities on the banks of Ganga is being managed by a mix of Interception & Diversion projects, sewerage network and sewage treatment plant (STP) projects.

The four stretches of river Ganga where Biological Oxygen Demand (BOD) levels are more than permissible limits, as monitored by Central Pollution Control Board (CPCB) is given in table below:

State
Stretch
Identified Length of Stretch (Km)
BOD range/ max value (mg/l)
Uttarakhand
Haridwar to Sultanpur Adampur
10
4.2-5.8
Uttar Pradesh
Kannauj to Varanasi
450
3.8-16.9
Bihar
Buxar to Bhagalpur
40
7.8-27
West Bengal
Tribeni to Diamond Harbour
50
3.1-5.8

In other stretches, BOD levels are within permissible limits i.e. =<3 mg/l. However, as per monitoring reports of CPCB, entire stretch of river Ganga has high levels of faecal coliform against the prescribed limits.

The detailed status of break-up of funds spent/released to the states from Financial Year 2014-15 to 2017-18 till 30.06.2017 are given below.                       
                                                                                                                    Rs. in crores
States
2014-15
2015-16
2016-17
2017-18
Grand Total
Bihar

120.23
82.03
0.20
202.46
Jharkhand
0.97
27.83
46.18
2.47
77.45
UP
74.58
147.58
587.17
38.22
847.55
Uttarakhand
4.26
30.26
30.66
16.26
81.44
West Bengal
73.85
185.79
114.25
0.11
374.00
Haryana
 
30.00
52.73
0.00
82.73
Delhi

4.96
2.17
2.66
9.79

This information was given by Union Minister of State for Water Resources, River Development and Ganga Rejuvenation Shri Vijay Goel in a written reply in Lok Sabha today. 


Courtesy: pib.nic.in