India Can Integrate 175 Gigawatts of Renewable Energy into the Electricity Grid, Reveals Study

Union Minister of State (IC) for Power, Coal, New & Renewable Energy, Shri Piyush Goyal released the first part of the study Pathways to Integrate 175 Gigawatts of Renewable Energy into Indias Electricity Grid at an event organized here today.  The second volume, to be released in July, takes a more in-depth look at system operations in the Western and Southern regions.

The study, developed under the U.S.-India bilateral program Greening the Grid, confirms the technical and economic viability of integrating 175 gigawatts (GWof renewable energy into Indias power grid by 2022, and identifies future course of actions that are favorable for such integration. The Government of India in 2015 had set the ambitious target of adding 100 GW of solar energy and 60 GW of wind energy into the countrys energy mix.

The report resolves many questions about how India’s electricity grid can manage the variability and uncertainty of adding large amounts of renewable energy into the grid. The results demonstrate that power system balancing with 100 GW solar and 60 GW wind is achievable at 15-minute operational timescales with minimal reduction in renewable energy output. India’s current coal-dominated power system has the inherent flexibility to accommodate the variability associated with the targeted renewable energy capacities.

Some of the key operational impacts that came out of the report were: (1) large-scale benefits of fuel savings and reduced emissions due to increased renewable energy production; (2) existing fast-ramping infrastructure is sufficient to maintain grid balance; and (3) in post-175 GW clean energy scenario, coal plants operating at part capacity will need suitable incentives for flexibility. The study also evaluates the value of strategies to better integrate renewable energy and demonstrates the importance of policy and market planning.

A multi-institutional team from Indias Power System Operation Corporation (POSOCOand the U.SDepartment of Energys National Renewable Energy Laboratory (NRELand Lawrence Berkeley National Laboratory (LBNL) produced the report using advanced weather and power system modeling, under the leadership of Ministry of Power and the U.SAgency for International Development (USAIDwith co-sponsorship from the World Bank Energy Sector Management Assistance Program (ESMAPand the 21st Century Power Partnership.

Speaking at the launch, Power Minister Piyush Goyal said: “It is time for the people of India to get ready and embrace the change with a New Mindset’ of a New Grid’ for a New India, which is ready to integrate large amount of renewable energyIt is appropriate time following on Honorable Prime Ministers meeting with the U.SPresident under a robust and focused U.S.-India Energy PartnershipThe ministry is extremely appreciative of the continued engagement and support from USAID and congratulates all the stakeholders including POSOCO, NREL, LBNL on the achievement of this outcomeCombined and collaborative efforts such as these are labour and data intensive and detailed and often go unsung but are critical to creating the backbone for a reliable grid.”

Highlighting the importance of the study and U.S.-India collaboration on clean energy, Michael Satin, Director of Clean Energy and Environment at USAID/India, said: “USAID has a long-standing collaboration with the Government of India in the area of energyEnergy is a key determinant of growth and India needs sustainable energy sources to continue to grow at 7-8 percent annuallyIntroducing renewable energy solutions into established energy systems often requires changes to well-established policy, institutions, and market structuresThis study will prove to be helpful in scaling up renewable energy in India effectively and sustainably.”

The results were based on a number of key assumptions including transmission planning existing within each state but not necessarily on corridors between states; compliance of all coal plants with the Central Electricity Regulatory Commission regulation that coal plants be able to operate at 55 percent of rated capacity; and a better load forecastInput data, assumptions and study results were validated extensively by more than 150 technical experts from central agencies including the Central Electricity Authority, Power Grid Corporation of India Ltd. (PGCIL), and NTPC; state institutions including grid operators, power system planners, renewable energy nodal agencies and distribution utilities; and the private sector, including renewable energy developers, thermal plant operators, utilities, research institutions, market operators and industry representatives.

Other Dignitaries present on the occasion were Shri P.K. Pujari, Secretary Power, Shri R.K. Verma, CEA Chairman, Shri K.V.S. Baba, CEO, POSOCO, Shri I.S Jha, CMD PGCIL and other senior officers from Ministries of Power and MNRE.



Courtesy: pib.nic.in