The work of construction of bridge over river Brahmputra to connect Dhola (Saikhowaghat) and Sadiya in upper Assam is in progress. 82% of the work is complete. Out of total nine milestones, seven have been achieved till date. The total cost of the project is Rs. 876 crore.
This information was given by Minister of State for Road Transport & Highways, Shri Pon. Radhakrishnan in a written reply to a question in the Lok Sabha today.
Courtesy: pib.nic.in