The details of the Allocation under Special Accelerated Development Programme in North- Eastern Region during last three years, year-wise:

Year
SARDP-NE (Allocation)
(Rs. in crore)
2011-12
1950
2012-13
1845
2013-14
2994


            The details of the work sanctioned during the last three year, year-wise is as under:

During 2011-12
Sl. No.
Project Name
State
Length
(km)
Cost  (In Rs. Cr)
Physical Progress
(%)
1.
2 laning from Nechipu to Hoj on BOT (Annuity) on NH-229
Arunachal Pradesh
311
1486
17.40
2
2 laning of NH-52B from Tissa-Longding-Khonsa bypass
Arunachal Pradesh
42.5
156.83
35.02
3
Improvement to double lane standards from km 806.75 to 832.00 of NH 52
Arunachal Pradesh
25.25
67.06
56.44
4
2 laning from Potin to Pangin on BOT (Annuity) on NH-229
Arunachal Pradesh
407
1985
0.00
5
2 laning Yinkion to Gobuk from km 0.000 (Yingkiong) to 25.200 (Gobuk) (Existing ch.0.00 to km 26.00)  (net length=25.200 km)
Arunachal Pradesh
25.20
106.25
33.04
6.
Improvement to double lane standards from km 0.00 to km 17.714 (Exist Km. 0.00 to Km 20.00) of Joram to Koloriang road
Arunachal Pradesh
17.714
106.9
26.85
7
Widening and strengthening of NH-52 from km 689.800 to 705.262 (Digaru-Tezu) to 2-lance standards
Arunachal Pradesh
15.485
53.74
25.57
8
Widening and strengthening of NH-52 from km 705.285 to km 717.675 (Tezu-Demwe) to 2-lance standards.
Arunachal Pradesh
12.39
38.14
19.53
9
2 laning Gobuk to Sijhon Nalla from Km26.210 (Gobuk) to 75.485 (Sijhon Nallha) (Existing ch.27.000-75.000) (net length = 49.275 km)
Arunachal Pradesh
49.275
207.03
17.36
10
Construction/improvement of Kumarghat – Kailashhar road to NHDL Tripura specification from km 0.00 (Kumarghat) to km. 24.775 (Kailashahar)
Tripura
24.775
90.75
22.00
11
Construction of new 2-lane roaod with paved shoulders Katticherra bypass from km.47.00 to km 52.00 of NH-154
Assam
5
48.38
59.60
12
Construction of new 2 lance road with paved shoulders from km.0.00 to km 3.500 of NH-154

Assam
3.5
53.15
76.66
13
Widening/strengthening of existing intermediate lance Goalpara-Solmari road to 2-lane Highways
Assam
7.9
14.58
40.50
14
Widening/strengthening of existing intermediate lane Barpeta-Howly road to 2-lance Highway (Length = 12.10 km)

Assam
12.1
22.63
91.00
15
Widening/strengthening of existing intermediate lane road to 2-lane highway from Rangajan Tinali (30th km of NH 30 ) to Golaghat Town (Length = 7.0 km)
Assam
7
11.59
Completed
16
Widening and strengthening of existing NH-31 A to double lane (Sevoke-Gangtok road) between km 4.475 to 14.075
West Bengal
8.88
51.11
45.24
17
Construction of 2-lance bypass at 9thmile of NH 31A
Sikkim
6.2
25.67
17.50
18
Construction of roadf from km 69.90 to 72.075 of NH 31A (Kapoor More) to NH double lane specification
Sikkim
2.175
10.49
6.00

Total (2011-12)

983
4535

During 2012-13
1
2 laning of Akajan-Likabali Bame road from km 97.00 to km 105.62 (new location km 103.174) (net length = 6.174 km) Basar-Bame)
Arunachal Pradesh
6.17
33.39
12.92
2
Widening/Strengthening of existing intermediate lane Gauripur-Dubhri Road to 2 lane Highway (length = 8.529 km)
Assam
8.59
22.09
85.00
3
Construction of new 2-lane road with paved shoulders to bypass Hilakandi town between km 18.800 and 26.00 of NH-154
Assam
9.75
48.48
43.10
4
Construction of two lane Melli-Manpur-Namchi road
Sikkim
32
182.28
18.00
5
Tender based estimate for 2 laning of Akajan-Likabali-Bame road from km.0.00 to km 12.00 (Akajan-Likabali)
Assam
12
32.62
20.75

Total (2012-13)

69
319


During 2013-14
1
Construction of 2 lane Jowai bypass between km 54.200 and km 69.200 (length = 7.997 km ) on NH-44
Meghalaya
7.997
46.62
9.00
2
Construction of two lane Nayabazar-Legship road
Sikkim
23.81
151.59
3.00
3
Construction of two lane Tarku-Damthang –Namchi Road
Sikkim
31.77
166.27
4.00

Total (2013-14)

64
364


           
            The Government under Special Accelerated Road Development Program-North East (SARDP-NE) has approved 6418 km length (Net length is 6137 km, based on Detailed Project Report) for implementation under Phase ‘A’ and the Arunachal Pradesh Package of Roads and Highways.  The length sanctioned so far is 3924 km and completed length is 1584 km.  The balance length is 2213 km and out of which 1913 is targeted for award during 2014-15 and balance 300 km during 2015-16.

        This was stated by General (Retd.) Dr. V K Singh, the Minister of State (Independent Charge) for Development of North East Region in Lok Sabha today.
Courtesy: pib.nic.in

No comments:

Extension of Emergency Credit Line Guarantee Scheme through ECLGS 2.0 for the 26 sectors identified by the Kamath Committee and the healthcare sector

Extension of the duration of Emergency Credit Line Guarantee Scheme (ECLGS) 1.0 The Government has extended Emergency Credit Line Guarantee ...