There is some deficiency in Border Roads Organisation (BRO) regarding staff, budget and equipment, however, this deficiency has not affected the construction of ICBRs.  Government has identified 73 roads as strategic Indo-China Border Roads (ICBR).  Out of the 73 roads, 61 roads have been entrusted to BRO with a length of 3417 km. 22 roads of length 707.24 km are  completed.  There  are  certain  delays  in  execution  of   road  projects mainly due to the following reasons:

·        Delay in Forest / Wildlife clearance.
·        Hard rock stretches.
·        Limited working season.
·        Difficulties in availability of construction material.
·        Delay in land acquisition.

The revised completion schedule of 39 ICBRs is as under:
o   2016      -  5 Roads.
o   2017      -  8 Roads.
o   2018      -  12 Roads.
o   2019      -   8 Roads.
o   2020      -   6 Roads.

Government has taken the following measures to expedite the pace of road projects:

·        States of Sikkim, Arunachal Pradesh, Jammu & Kashmir, Himachal Pradesh and Tripura have constituted the Empowered Committee to resolve issues related to land acquisition, forest / wildlife clearance, allotment of quarries etc.
·        Outsourcing has been allowed to augment capacity of BRO.
·        Long Term Roll On Works Plan (LTROWP) and Long Term Equipment Plan (LTEP) have been approved.
·        Enhanced financial and administrative powers have been given to the executives of BRO.

This information was given by Minister of State for Defence Dr. Subhash Bhamre in a written reply to Dr. Shashi Tharoor in Lok Sabha today.


Courtesy: pib.nic.in